HS2's new A45 bridge near Birmingham Airport reaches halfway, with traffic switching over from 7 December

The first half of the Coventry Road overbridge is built. Overnight and weekend closures start on 7 December, and the full bridge should be in use by summer 2028.

Discover Brum Newsdesk

3 min read

Aerial view of HS2 construction works beside roads near the NEC and Birmingham Airport
Aerial view of HS2 construction works beside roads near the NEC and Birmingham Airport. Photo: Thomas Nugent / Wikimedia Commons, CC BY-SA 2.0

The new bridge that will carry the A45 Coventry Road over HS2's tracks near Birmingham Airport has reached the halfway mark, and drivers will start using the first finished half within weeks, with overnight and weekend closures from 7 December to switch the traffic over.

Over the past 11 months, engineers working for HS2's construction partner Balfour Beatty VINCI have completed the first section of the Coventry Road overbridge near Bickenhill. The bridge is being built in two halves so that traffic can keep flowing in both directions, minimising the impact on local roads, Rail Business Daily reported.

Built from the top down

Using a "top down" method, the team dug out earth from beneath the existing carriageway, installed 46 piles at depths of up to 23 metres, and built pile caps to carry the 2,000-tonne bridge deck. Over the summer, 13 pre-stressed concrete beams were lowered into place to support the 37-metre span, and 13 parapet units were fitted to one half of the structure.

Below, hidden from view, the team will keep digging the cutting that will eventually carry four railway tracks towards HS2's Interchange station, just a mile away. The station will have four platforms on two 425-metre-long islands.

What drivers need to know

Waterproofing and road works will be finished in the coming weeks, and the eastbound section of the new bridge will then be brought into use. HS2 is working with National Highways on the traffic changes, with a series of overnight and weekend closures from Monday 7 December. After that, drivers will use a temporary road layout across the new eastbound section.

Paul Marshall, head of delivery at HS2 Ltd, said: "Our engineers have worked incredibly hard to develop a design solution that maintains traffic flows in each direction, while we build the bridge and excavate the ground below to make way for the new high-speed railway."

"During the temporary weekend and night-time closures, to facilitate the traffic switchover onto the new bridge, we'll ensure that access to businesses and properties is maintained. I'd encourage motorists to familiarise themselves with the diversion routes and thank them for their patience."

Finished by 2028

Work on the second half of the bridge starts in the new year, following the same sequence. Richard Husbands, Balfour Beatty VINCI's project manager, said: "Construction of the bridge in two halves is a complex engineering challenge, and reaching the halfway stage is an important milestone for the project. The programme we're working to has been designed to minimise disruption for motorists and local communities as much as possible."

The bridge is expected to be structurally complete by the end of 2027. Engineers will then fit lighting, kerbs, drainage and the permanent road surface, with the finished bridge and road layout expected to be in use by summer 2028.

All