Dudley Road upgrade finished, with cycle lanes, bus lanes and safer crossings to Midland Met
The four-phase A457 scheme between Birmingham and Sandwell is complete, aiming for reliable buses, safer walking and cycling and less congestion.
The final stage of the Dudley Road improvement scheme has been completed, giving one of Birmingham's busiest routes segregated cycle lanes, enforced bus lanes and safer crossings, and better links to Midland Metropolitan University Hospital.
The A457 Dudley Road links Birmingham and Sandwell. The council says the scheme is designed to make the road safer, encourage walking and cycling, cut journey times for buses and support new housing along the corridor.
"This had to change"
Councillor Rob Grant, cabinet member for transport, said: "For too long this key route between Birmingham and Sandwell has been dominated by private vehicles moving slowly along a regularly congested route."
"This meant bus travel was unreliable, and the route was undesirable for people wishing to walk, wheel or cycle, with no facilities for pedestrians and cyclists to cross safely at busy intersections. This had to change. The new road means it is safer and more encouraging for people to walk and cycle, bus journeys are smoother and quicker, and for those who need to drive there is far less congestion."
Council leader Roger Harmer thanked residents, commuters and hospital patients for their patience. "The real measure of success will be the buses that arrive on time, children crossing the road to school safely, commuters that have a smooth journey to work and more people taking the opportunity to walk or cycle," he said.
Better access to Midland Met
Kevin Reynolds, Head of Estates at Sandwell and West Birmingham NHS Trust, said the scheme was an important milestone "for the thousands of patients, visitors and NHS staff who travel to Midland Metropolitan University Hospital every day", making journeys "safer, easier and more reliable whether people are travelling by bus, car, bicycle or on foot".
Four phases of work
- Phase 1, the Western Road junction, was finished in May 2022, improving the junction and opening up access to around 3,000 new homes at the Soho Loop development.
- Phase 2, covering Spring Hill, the Barford Estate and the Heath Street and Winson Green Road sections, was finished in August 2024. It added tidal flow bus lanes, a bus lane camera, segregated cycle lanes, better crossings and a new walking and cycling bridge next to the Spring Hill canal bridge.
- Phase 3, the Lee Bridge and Icknield Port Road junction section between City Hospital and Summerfield Park, was finished in April 2026.
- Phase 4, a cycle track at the Birmingham Treatment Centre, began in January 2026 and was finished in October.
The work was carried out by contractor McPhillips for Birmingham City Council. Director Andrew Dunham said rebuilding the route "while keeping traffic moving and City Hospital accessible took careful planning", and thanked everyone who travels along Dudley Road for their patience.
More in Transport
All
Latest news
Featured posts
-
Things to do
Top 10 places to visit in Birmingham
-
Food and drink
The 12 most popular food spots in Birmingham
-
Things to do
The best laser tag locations in Birmingham